Follow the steps below to enable integration of the start and end dates for the Timeline with Jira.

Configure Jira Fields

  • Go to ALM Accounts (Settings option is only visible to Kendis Super Admins of your organization)

  • Edit ALM Account

  • Click on Test Connection

  • Select the Start and End Dates Fields from Jira

Bi-directional Updates

  • The dates at the Kendis Program Board are only linked to your Features/Jira Epics. There is no option to set the dates for integration between Kendis and Jira.

  • Updates From Jira to Kendis: If your webhook is working, any changes made in JIra will appear automatically in Kendis

  • Updates from Kendis to Jira:

    • Update by editing the Feature Detail View

    • At Timeline, go to "By Date."

    • To set the date of a feature, drag the bar a bit, and it will show the dates edit option.
      ​